Port Gamble S’Klallam Tribe Hood Canal Bridge Fish Passage Mitigation

Salmonid Habitat Restoration and Acquisition

Fish Passage Improvement
Project ID23-PORT-02
Recovery Domains -
Start Date02/01/2024
End Date06/30/2026
Year2023
StatusNew
Last Edited11/19/2024
 
1 - 1

Description    


This project will entail implementing and testing on-the-ground measures to reduce the impacts stemming from the presence of the Hood Canal Bridge. The Hood Canal Bridge is a migration barrier to juvenile salmonids, including ESA-listed Puget Sound steelhead, Puget Sound Chinook, and Hood Canal summer chum. This implementation project, which includes several components including design, fabrication, deployment, and operations will primarily help fund the operations and adaptive management of two fish guidance structures “fillets” on the Hood Canal Bridge. The structures will be deployed to facilitate fish passage and alter fish/predator behavior in the project area (The project area was identified as a high predation zone during phase 1 of the Hood Canal Bridge Ecosystem Assessment). In addition to assisting in the deployment and development of the structures, the Tribe will use visual acoustics (multibeam imaging sonar), and remote underwater video to ensure that the structures are functioning as designed. Post-deployment results will indicate whether the fish guidance structures; alter fish/predator behavior and increase the probability of juvenile steelhead survival.

Project Benefit    


This project will help forward Phase 2 of the Hood Canal Bridge Ecosystem Assessment which is designed to: 1) implement and iterate on the highest priority management actions recommended through the Phase 1 process. and 2) address remaining high priority knowledge gaps regarding bridge impacts on juvenile Chinook and chum salmon, and adult salmon returning to natal Hood Canal watersheds.

Accomplishments

Metric Completed Originally
Proposed
Fish Passage
  Barriers Removed 1
  Miles Opened 72.00

Funding Details

No Funding data has been entered for this project.


Project Map



Worksites

54461903    


  • Worksite Identifier: 54461903
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Puget Sound (171100)
  • Subbasin: Hood Canal (17110018)
  • Watershed: Hood Canal (1711001808)
  • Subwatershed:
  • State: Washington
  • Recovery Domain:
  • Latitude: 47.854354
  • Longitude: -122.614835

ESU

  • Puget Sound/Strait of Georgia Coho Salmon ESU
  • Hood Canal Summer-run Chum Salmon ESU
  • Puget Sound Steelhead DPS
  • Puget Sound Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding .00
    •      . . C.0.b Length of stream treated/protected
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding
      •      . . . . C.2.b.1 Length of stream made accessible
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage
      •      . . . . C.2.c.1 Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
        •      . . . . . . C.2.c.2 Number of blockages/impediments/barriers removed/altered
      •      . . . . C.2.d.1 Fishway chutes or pools installedY (Y/N)
        •      . . . . . . C.2.d.2 Number of fishway chutes/pools installed