Loon Creek Habitat Improvement Project- Headgate

Salmonid Habitat Restoration and Acquisition

Fish Screening
Project ID021 19 SA
Recovery DomainsSnake River
Start Date01/01/2023
End Date08/30/2023
Year2019
StatusCompleted
Last Edited02/27/2024
 
1 - 1

Description    


Headgate installation was the final action for the Loon Creek Habitat Improvement Project (PCSRF Project 014 18 SA) to prevent Snake River Spring/Summer-run Chinook Salmon and Snake River Steelhead from being entrained in a private lake at the Diamond D Ranch. The headgate functions in accordance with an already installed fish screen and will provide adequate water to fill the penstock pond to provide water to the new hydro facility.

Project Benefit    


Installation of the fish screen was completed under the Loon Creek Habitat Improvement Project (PCSRF Project 014 18 SA) along with other habitat actions. The screen is self-cleaning, and will be used Spring through Fall to prevent salmonid entrainment in the Diamond D lake during the migration season. Installation of the headgate was delayed due to identifying redds immediately downstream of the new POD and it could not be completed in the timeframe of PCSRF Project 014 18 SA. The headgate will be installed in summer 2023 during the fish window.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$23,850
Other$3,468
Report Total:$27,318


Project Map



Worksites

Diamond D Ranch    


  • Worksite Identifier: Diamond D Ranch
  • Start Date: 06/20/2023
  • End Date: 08/30/2023
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Salmon (170602)
  • Subbasin: Upper Middle Fork Salmon (17060205)
  • Watershed: Upper Loon Creek (1706020510)
  • Subwatershed: Mayfield Creek (170602051003)
  • State: Idaho
  • Recovery Domain: Snake River
  • Latitude: 44.55
  • Longitude: -114.85

ESU

  • Snake River Basin Steelhead DPS
  • Snake River Spring/Summer-run Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 27,318.00
    •      . . C.0.b Length of stream treated/protected .01
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      NMFS 2017. ESA Recovery Plan for Snake River Spring/Summer Chinook Salmon (Oncorhynchus tshawytscha) & Snake River Basin Steelhead (Oncorhynchus mykiss).
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.1 Fish Screening ProjectY (Y/N)
      •      . . . . C.1.a Fish screen funding 27,318.00
      •      . . . . C.1.b Quantity of water protected by screens 7600 (Acre feet/year)
      •      . . . . C.1.d.1 Fish screens replaced or modifiedY (Y/N)
        •      . . . . . . C.1.d.2 Number of fish screens replaced or modified 1
        •      . . . . . . C.1.d.3 Flow rate of screened water 7600 (cfs)