James Creek Coho Stream Habitat Enhancement Project-Phase II

Salmonid Habitat Restoration and Acquisition

Instream Habitat
Project ID725527
Recovery DomainsN Central California Coast
Start Date06/01/2018
End Date09/08/2021
Year2017
StatusCompleted
Last Edited04/14/2022
 
1 - 1

Description    


The project is now complete. Some sites were modified with the approval of the CDFW contract manager. No fish relocation or dewatering was required for this project. A total of 49 pieces of wood were installed at 18 features along 0.4469 mi.(2,360 ft) of creek.

Project Benefit    


The expected result of this project is to have 20 structures containing a total of 47 pieces of large woody debris installed in a 2,350 foot reach of high priority salmonid habitat in James Creek. These structures are expected to increase stream complexity, pool frequency, rearing habitat, and add velocity refuge during peak winter flows.

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated .43 .45

Funding Details

SourceFunds
PCSRF$115,461
In-Kind Donated Labor$60,551
In-Kind Other$1,253
Report Total:$177,265


Project Map



Worksites

7211130    


  • Worksite Identifier: 7211130
  • Start Date:
  • End Date:
Area Description
Site 1

Location Information

  • Basin: Northern California Coastal
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 39.37609
  • Longitude: -123.49836

ESU

  • California Coastal Chinook Salmon ESU
  • Central California Coast Coho Salmon ESU
  • Northern California Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 177,265.00
    •      . . C.0.b Length of stream treated/protected .43
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      National Marine Fisheries Service, 2016, Coastal Multispecies Recovery Plan, National Marine Fisheries Service, Santa Rosa, CA
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 177,265.00
      •      . . . . C.4.b Total length of instream habitat treated .43
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .43
        •      . . . . . . C.4.d.5 Pools expected to be created through channel structure placement 0
        •      . . . . . . C.4.d.7 Number of structures placed in channel 19