Fish Passage and Off-Channel Habitat Restoration at Roy's Pools
Salmonid Habitat Restoration and Acquisition
|
725512 | N Central California Coast | 07/01/2018 | 08/12/2022 | 2017 | Completed | 01/25/2024 | |
| |
Description
The project removed a fish barrier known as Roys Pools. This structure consisted of a concrete dam, roughly 15 feet tall, a narrow fish ladder, and four sheet metal weirs downstream of the dam. During the summer of 2020 and again in 2021 (August- October) all man-made structures, including the dam, weirs, and fish ladder were removed. A series of rock grade control vanes and a mix of engineered streambed material (ESM) was placed on top of and between the rock vanes. A segment of the stream was relocated to the north to aid in alignment and long-term stability. The original main channel became a new seasonal side channel, which sees flows during flood events. Two LWD structures, with accompanied willow living debris clusters were placed in two pools upstream of the former dam site. A failing pedestrian bridge at the location of the dam site was removed and replaced with a full-span pedestrian bridge for trail users over the creek.
Project Benefit
Removal of the dam will provide access to 3.5 miles of upstream habitat.
Accomplishments
Instream Habitat |
Stream Miles Treated |
.09 |
.20 |
Fish Passage |
Barriers Removed |
1 |
1 |
Miles Opened |
5.00 |
3.50 |
Funding Details |
PCSRF | $2,115,705 |
In-Kind Donated Labor | $186,532 |
Report Total: | $2,302,237 |
|
| |
Worksites
7211114
- Worksite Identifier: 7211114
- Start Date:
- End Date:
Area Description
Roy's Pools
Location Information
- Basin: San Francisco Bay (180500)
- Subbasin: Tomales-Drake Bays (18050005)
- Watershed: Lagunitas Creek (1805000501)
- Subwatershed: San Geronimo Creek-Lagunitas Creek (180500050103)
- State: California
- Recovery Domain: N Central California Coast
- Latitude: 38.01253
- Longitude: -122.662822
ESU
- Central California Coast Coho Salmon ESU
- Central California Coast Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 3,342,388.00
- . . C.0.b
Length of stream treated/protected .10
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
NOAA CCC ESU Recovery Plan 2012
LagC-CCC-6.1.1.1 |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.2
Fish Passage ImprovementY (Y/N)
- . . . . C.2.a
Fish Passage Funding 2,271,646.00
- . . . . C.2.b.1
Length of stream made accessible 5.00
- . . . . C.2.b.3
Type of blockage/barrier (LOV)
- . . . . C.2.b.4
Number of blockages/impediments/barriers impeding passage 1
- . . . . C.2.c.1
Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
- . . . . . . C.2.c.2
Number of blockages/impediments/barriers removed/altered 1
- . . . . C.2.d.1
Fishway chutes or pools installedY (Y/N)
- . . . . . . C.2.d.2
Number of fishway chutes/pools installed 5
- . . . . C.2.g.1
Bridge installed or improved at road stream crossingY (Y/N)
- . . . . . . C.2.g.2
Number of bridges installed or improved/upgraded 1
- . . . . . . C.2.g.3
Miles of stream made accessible by bridge installation or improvement/upgrade 5.00
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 1,070,742.00
- . . . . C.4.b
Total length of instream habitat treated .09
- . . . . C.4.c.1
Channel reconfiguration and connectivityY (Y/N)
- . . . . . . C.4.c.2
Type of change to channel configuration and connectivity (LOV)
- . . . . . . C.4.c.3
Miles of stream treated for channel reconfiguration and connectivity .09
- . . . . . . C.4.c.4
Miles of off-channel stream created through channel reconfiguration and connectivity 5.00
- . . . . . . C.4.c.6
Instream pools created/added through channel reconfiguration and connectivity 5
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement .09
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 5
- . . . . . . C.4.d.6
Yards of average stream-width at mid-point of channel structure placement project7 (Yards)
- . . . . . . C.4.d.7
Number of structures placed in channel 5
|
|