Chamberlain Creek Coho Passage Design Project
Salmonid Restoration Planning and Assessments
|
1611968198576 | N Central California Coast | 06/07/2021 | 12/31/2024 | 2020 | Ongoing | 06/23/2022 | |
| |
Description
This project will address CDFW recovery priorities on Chamberlain Creek in the Big River watershed by designing a remedy for a fish passage barrier posed by a corrugated metal pipe that partially prevents adult, juvenile coho, and lamprey passage to 1.6 miles of suitable upstream habitat. The project will design a new stream crossing that will meet fish passage, hydraulic capacity, and debris load requirements. Project partners will evaluate the instream habitat throughout the project as part of scoping and feasibility studies.
Project Benefit
The primary expected benefit of this design proposal is year-round passage for adult and juvenile coho to 1.6 miles of suitable upstream habitat. As additional benefits, the design will ensure hydraulic capacity and meet debris load requirements.
Funding Details |
PCSRF | $118,966 |
In-Kind Donated Labor | $2,618 |
Report Total: | $121,584 |
|
| |
Worksites
1611968198792
- Worksite Identifier: 1611968198792
- Start Date:
- End Date:
Area Description
Culvert on Main Chamberlain Road
Location Information
- Basin: Northern California Coastal
- Subbasin:
- Watershed:
- Subwatershed:
- State: California
- Recovery Domain: N Central California Coast
- Latitude: 39.383409
- Longitude: -123.547675
ESU
- California Coastal Chinook Salmon ESU
- Central California Coast Coho Salmon ESU
- Northern California Steelhead DPS
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding .00
- . . B.0.b.1
Area Encompassed
- . . B.0.b.2
Stream Miles Affected
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding
- . . . . B.1.b.8
Conducting habitat restoration scoping and feasibility studiesY (Y/N)
- . . . . . . B.1.b.8.a
- . . . . . . B.1.b.8.b
Description and scope of the plan implemented | |
|
- . . . . B.1.b.11
Engineering/design work for restoration projectsY (Y/N)
- . . . . . . B.1.b.11.a
- . . . . . . B.1.b.11.b
Description and scope of the plan implemented | |
|
|
|