Inman Creek Sediment Reduction Project
Salmonid Habitat Restoration and Acquisition
|
1551968924232 | N Central California Coast | 06/01/2019 | 02/18/2021 | 2018 | Completed | 04/08/2022 | |
| |
Description
Grantee decommissioned approximately 1.6 miles of road to reduce threats of episodic inputs of sediment from larger road failures during large magnitude storms and floods. Prescribed treatments hydrologically disconnected road surfaces from the adjacent watercourse, prevented fill failures, stream crossing washouts and stream diversions. As a result, further degradation of water quality and salmonid habitat has been reduced. The project was implemented as stated in the road log that was included with the original proposal. No changes were needed in the field during implementation.
Project Benefit
This project will address legacy impact created by sediment discharge from old forest roads. Abandonment and stabilization of watercourse crossings with high sediment delivery risk will result in approximately 2,000 cubic yards of potential sediment from being delivered to Inman Creek and will improve instream habitat conditions for spawning and rearing salmonids.
Accomplishments
Upland Habitat |
Acres Treated |
3.9 |
3.9 |
Funding Details |
State | $46,318 |
In-Kind Donated Labor | $18,284 |
Report Total: | $64,603 |
|
| |
Worksites
1551968924408
- Worksite Identifier: 1551968924408
- Start Date:
- End Date:
Area Description
Worksite 1
Location Information
- Basin: Northern California Coastal
- Subbasin:
- Watershed:
- Subwatershed:
- State: California
- Recovery Domain: N Central California Coast
- Latitude: 38.88218
- Longitude: -123.4328
ESU
No ESU data was found for this worksite.
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 40,039.00
- . . C.0.b
Length of stream treated/protected 1.10
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
CA Department of Fish and Wildlife, 2004, Recovery Strategy for CA Coho Salmon |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 40,039.00
- . . . . C.6.b.1
Acres of upland habitat area treated 2.7
- . . . . C.6.b.2
Miles of road treated in upland area 1.10
- . . . . C.6.b.3
Cubic yards (to nearest yard) of sediment prevented from entering stream1638 (Cubic yards)
- . . . . C.6.d.1
Road closure / abandonmentY (Y/N)
- . . . . . . C.6.d.2
Miles of road closed / abandoned 1.10
1551968924412
- Worksite Identifier: 1551968924412
- Start Date:
- End Date:
Area Description
Worksite 2
Location Information
- Basin: Northern California Coastal
- Subbasin:
- Watershed:
- Subwatershed:
- State: California
- Recovery Domain: N Central California Coast
- Latitude: 38.897
- Longitude: -123.43801
ESU
No ESU data was found for this worksite.
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 24,563.00
- . . C.0.b
Length of stream treated/protected .50
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
CA Department of Fish and Wildlife, 2004, Recovery Strategy for CA Coho Salmon |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 24,563.00
- . . . . C.6.b.1
Acres of upland habitat area treated 1.2
- . . . . C.6.b.2
Miles of road treated in upland area .50
- . . . . C.6.b.3
Cubic yards (to nearest yard) of sediment prevented from entering stream362 (Cubic yards)
- . . . . C.6.d.1
Road closure / abandonmentY (Y/N)
- . . . . . . C.6.d.2
Miles of road closed / abandoned .50
|
|