FY 2020 Squaxin Island Tribe South Sound Trapping
Salmonid Research, Monitoring, and Evaluation (RM&E)
|
20-squax-02 | Puget Sound | 01/01/2023 | 06/30/2023 | 2020 | Completed | 02/27/2024 | |
| |
Description
As part of continuous monitoring, the Tribe placed a panel weir trap in Cranberry Creek and rotary screw traps in Goldsborough, Skookum, and Mill Creeks. Traps were placed in March, fished 24 hours a day, seven days a week, and removed in June to target out-migrating coho smolts. Information obtained included the number of smolts, length, condition, and migration timing.
While coho was the species of interest, all trapped encounters were enumerated and measured. The trapping program was targeted toward systems with substantial restoration and conservation potential.
Project Benefit
Ongoing monitoring of out-migrating coho smolts and the returning escapement measures productivity and survival as well as providing information on freshwater restoration efforts. This information is essential to managing harvest by providing population scale estimates of abundance and secondarily for planning and monitoring the effectiveness of habitat restoration efforts.
Accomplishments
Research and Monitoring |
Stream Miles Monitored |
48.40 |
48.40 |
Funding Details |
PCSRF | $75,933 |
Report Total: | $75,933 |
|
| |
Worksites
48599936
- Worksite Identifier: 48599936
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Puget Sound (171100)
- Subbasin: Puget Sound (17110019)
- Watershed: Goldsborough Creek-Frontal Puget Sound (1711001906)
- Subwatershed: Skookum Creek-Frontal Little Skookum Inlet (171100190603)
- State: Washington
- Recovery Domain: Puget Sound
- Latitude: 47.122513721
- Longitude: -123.081836799
ESU
- Puget Sound/Strait of Georgia Coho Salmon ESU
Map
Photos
Metrics
Metrics
- E.0
Salmonid Research, Monitoring, and Evaluation (RM&E)Y (Y/N)
- . . E.0.a
RM&E Funding 75,933.00
- . . E.0.b
Complement habitat restoration project | |
None |
- . . E.0.c
Project identified in a plan or watershed assessment. | |
None |
- . . E.0.d.1
Number of Cooperating Organizations 0
- . . E.0.d.2
Name Of Cooperating Organizations. | |
None |
- . . E.0.e.1
Number of reports prepared 0
- . . E.0.e.2
- . . E.1
MonitoringY (Y/N)
- . . . . E.1.a
Monitoring funding 75,933.00
- . . . . E.1.b.1
Stream Miles Monitored 48.40
- . . . . E.1.b.2
Acres of Watershed Area Monitored .0
- . . . . E.1.b.3
Square miles of water monitored0 (Square miles)
- . . . . E.1.c.2
Salmonid smolt or fry monitoringY (Y/N)
- . . . . . . E.1.c.2.a
# miles (to nearest 0.01 mile) monitored for Salmonid smolt or fry 48.40
- . . . . E.1.d
Name Of Comprehensive Monitoring Strategy/Program | |
None |
|
|