West Fork Millicoma Habitat Improvements and Road Decommission
Salmonid Habitat Restoration and Acquisition
|
OWEB 210-2066-7882 | Oregon Coast | 05/21/2010 | 08/06/2014 | 2009 | Completed | 07/21/2022 | |
| |
Description
This project placed large wood instream at Worksite 20110070; installed a log and rock/boulder flow deflector at Worksite 20110071; replaced a culvert with a culvert at Worksite 20140018; and decommissioned a road and treated the road drainage system by removing log fills or culverts at Worksite 20140019.
Project Benefit
-EWs and Upper Elk Creek wood placements will improve in-stream habitat complexity in 1 mile of the West Fork Millicoma River and in 2 miles of Upper Elk Creek, improving spawning and rearing habitat for coho salmon and winter steelhead. The 1600 road decommission will benefit salmon and steelhead by improving water quality and reducing the amount of fine sediment in spawning gravels. It will also help to reduce peak flows that may scour crucial spawning gravels
Accomplishments
Instream Habitat |
Stream Miles Treated |
2.75 |
|
Upland Habitat |
Acres Treated |
31.9 |
|
Fish Passage |
Barriers Removed |
|
|
Miles Opened |
.30 |
|
Funding Details |
State | $200,955 |
In-Kind Donated Labor | $9,600 |
In-Kind Other | $100,100 |
Report Total: | $310,655 |
|
| |
Worksites
20110070
- Worksite Identifier: 20110070
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Southern Oregon Coastal
- Subbasin:
- Watershed:
- Subwatershed:
- State: Oregon
- Recovery Domain: Oregon Coast
- Latitude: 43.52948307
- Longitude: -123.92815088
ESU
- Oregon Coast Coho Salmon ESU
- Oregon Coast Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 150,294.77
- . . C.0.b
Length of stream treated/protected 2.00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Elliott State Forest Watershed Analysis/2003/ODF |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 150,294.77
- . . . . C.4.b
Total length of instream habitat treated 2.00
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement 2.00
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 25
- . . . . . . C.4.d.7
Number of structures placed in channel 27
20140018
- Worksite Identifier: 20140018
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Southern Oregon Coastal
- Subbasin:
- Watershed:
- Subwatershed:
- State: Oregon
- Recovery Domain: Oregon Coast
- Latitude: 43.57553453
- Longitude: -123.93672251
ESU
- Oregon Coast Coho Salmon ESU
- Oregon Coast Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 19,060.85
- . . C.0.b
Length of stream treated/protected .01
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Elliott State Forest Watershed Analysis/2003/Oregon Department of Forestry |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.2
Fish Passage ImprovementY (Y/N)
- . . . . C.2.a
Fish Passage Funding 19,060.85
- . . . . C.2.b.1
Length of stream made accessible .30
- . . . . C.2.b.3
Type of blockage/barrier (LOV)
- . . . . C.2.b.4
Number of blockages/impediments/barriers impeding passage 1
- . . . . C.2.f.1
Culvert installed or improved at road stream crossingY (Y/N)
- . . . . . . C.2.f.2
Number of culverts installed or improved 1
- . . . . . . C.2.f.3
Miles of stream made accessible by culvert installation/upgrade .30
20140019
- Worksite Identifier: 20140019
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Southern Oregon Coastal
- Subbasin:
- Watershed:
- Subwatershed:
- State: Oregon
- Recovery Domain: Oregon Coast
- Latitude: 43.53766678
- Longitude: -123.92211919
ESU
- Oregon Coast Coho Salmon ESU
- Oregon Coast Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 14,200.41
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Elliott State Forest Watershed Analysis/2003/Oregon Department of Forestry |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 14,200.41
- . . . . C.6.b.1
Acres of upland habitat area treated 31.9
- . . . . C.6.b.2
Miles of road treated in upland area 2.63
- . . . . C.6.c.1
Road drainage system improvements and reconstructionY (Y/N)
- . . . . . . C.6.c.2
Miles of road treated for drainage system improvements and reconstruction .83
- . . . . C.6.d.1
Road closure / abandonmentY (Y/N)
- . . . . . . C.6.d.2
Miles of road closed / abandoned 1.80
20110071
- Worksite Identifier: 20110071
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Southern Oregon Coastal
- Subbasin:
- Watershed:
- Subwatershed:
- State: Oregon
- Recovery Domain: Oregon Coast
- Latitude: 43.57585178
- Longitude: -123.96089018
ESU
- Oregon Coast Coho Salmon ESU
- Oregon Coast Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 127,098.97
- . . C.0.b
Length of stream treated/protected .75
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Elliott State Forest Watershed Analysis/2003/ODF |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 127,098.97
- . . . . C.4.b
Total length of instream habitat treated .75
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement .75
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 4
- . . . . . . C.4.d.7
Number of structures placed in channel 8
|
|