Suquamish Tribe FY 2019 West Sound Salmon and Steelhead Recovery Planning and Coordination

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID19-SUQU-01
Recovery DomainsPuget Sound
Start Date03/01/2023
End Date06/30/2025
Year2019
StatusCompleted
Last Edited10/20/2025
 
1 - 1

Description    


This project continued the Suquamish Tribes focus on salmon and steelhead recovery planning, coordination, and project implementation within its Usual and Accustomed Fishing Area (U&A). Specifically, this project focused on coordinating implementation of 1) Local chapter of the Puget Sound Chinook Salmon Recovery Plan (2005) and Puget Sound Steelhead Recovery Plan (completed in 2020) through participation in the West Sound Partners for Ecosystem Recovery (WSPER - the East Kitsap Lead Entity for Salmon Recovery) and the Puget Sound Salmon Recovery Council; this project also included the Suquamish Tribes participation during 2024 and 2025 in the update of the now completed local chapter of the Salmon Recovery Plan (the updated plan is now multi-species and focused on both watershed and nearshore habitat conditions and priorities for recovery), 2) Strategies and actions addressing factors affecting abundance, productivity, spatial structure, and diversity of salmon and steelhead populations important to the exercise of the Suquamish Tribes treaty rights.



Specifically, to support the East Kitsap Steelhead Recovery Plan, the Tribe allocated $44,944 of PCSRF FY19 to contract with a consultant to support the development of the East Kitsap Steelhead Population Monitoring Plan, a recommendation from the 2020 East Kitsap Steelhead Recovery Plan. The tasks and deliverables of this project included 1) two meetings of a focus group convened by the Tribe and the consultant to identify approaches and methods for monitoring ESA-listed steelhead populations in the East Kitsap Demographically Independent Population (DIP), 2) The compilation of reports and publications to support the monitoring plan, and 3) A technical memorandum (see attached) that describes the major findings of the focus group meetings and outlines a draft of a monitoring plan. The Tribe will allocate about $35,000 of PCSRF FY22 to the development of a draft and final East Kitsap Steelhead Monitoring Plan, scheduled for completion by December 31, 2025.

Project Benefit    


The goal is to maintain the Tribes participation in salmon recovery planning and implementation. The project purpose is well coordinated salmon recovery efforts in East Kitsap. The expected benefit is more effective protection and restoration of freshwater, estuarine, and nearshore habitat necessary to support recovery of listed salmonids and to prevent future listings.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$163,859
Report Total:$163,859


Project Map



Worksites

46812936    


  • Worksite Identifier: 46812936
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Puget Sound (171100)
  • Subbasin: Puget Sound (17110019)
  • Watershed: Olalla Valley-Frontal Puget Sound (1711001907)
  • Subwatershed: Big Valley-Frontal Puget Sound (171100190707)
  • State: Washington
  • Recovery Domain: Puget Sound
  • Latitude: 47.712538
  • Longitude: -122.570667

ESU

  • Puget Sound Chinook Salmon ESU
  • Puget Sound/Strait of Georgia Coho Salmon ESU
  • Puget Sound/Strait of Georgia Chum Salmon ESU
  • Puget Sound Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 163,859.00
    •      . . B.0.b.1 Area Encompassed 270,000.0
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding 163,859.00
      •      . . . . B.1.b.2 Coordination on implementation of a Recovery PlanY (Y/N)
        •      . . . . . . B.1.b.2.a
          Name of the Recovery Plan Implemented
          Shared Strategy Development Committee and National Marine Fisheries Service. 2007. Puget Sound Salmon Recovery Plan for the Puget Sound Chinook Salmon (Oncorhynchus tshawytscha). Comprised of two documents: 1) Shared Strategy Development Committee, 2005, Puget Sound Salmon Recovery Plan, Volumes I and II, adopted by the National Marine Fisheries Service on January 19, 2007; and 2) NMFS, 2006, Final Supplement to the Shared Strategy's Puget Sound Salmon Recovery Plan. East Kitsap Steelhead Demographically Independent Population (DIP) Recovery Plan (2020).
        •      . . . . . . B.1.b.2.b
          Description and scope of the Recovery Plan implemented
          This project supported planning and coordinating the implementation of the East Kitsap and Nearshore Chapters of the PS Salmon Recovery Plan, and its 2025 update; the PS Steelhead Recovery Plan (2019), including the local recovery plan covering the East Kitsap Steelhead DIP.
      •      . . . . B.1.b.9 Evaluation/analysis of restoration plans and projectsY (Y/N)
        •      . . . . . . B.1.b.9.a
          Name of plan implemented
          Shared Strategy Development Committee and National Marine Fisheries Service. 2007. Puget Sound Salmon Recovery Plan for the Puget Sound Chinook Salmon (Oncorhynchus tshawytscha). Comprised of two documents: 1) Shared Strategy Development Committee, 2005, Puget Sound Salmon Recovery Plan, Volumes I and II, adopted by the National Marine Fisheries Service on January 19, 2007; 2) NMFS, 2006, Final Supplement to the Shared Strategy's Puget Sound Salmon Recovery Plan; and 3) ESA, 2020. East Kitsap Steelhead DIP Recovery Plan.
        •      . . . . . . B.1.b.9.b
          Description and scope of the plan implemented
          This project supports salaries that evaluate and analyze restoration plans and projects contained in the West Sound habitat work schedule, which captures implementable actions under the East Kitsap chapter of the PS Recovery Plan. This project also supports salaries that help coordinate the implementation of salmonid protection and restoration actions under the East Kitsap Steelhead DIP Recovery Plan, and the development of a East Kitsap Steelhead DIP Monitoring Plan, which has been initiated using FY19 funds.