Scott River, Mill-Shackelford Creek Bridge

Salmonid Habitat Restoration and Acquisition

Fish Passage Improvement
Project ID725150
Recovery DomainsN CA - S Oregon
Start Date06/30/2017
End Date03/26/2019
Year2016
StatusCompleted
Last Edited01/25/2024
 
1 - 1

Description    


Decommission low water road crossing impacting salmonid habitat by vehicle usage. Installed bridge to meet 100 year flood and vehicle weight criteria replacing the ford crossing.

Project Benefit    


Increase accessible habitat to juvenile coho during all flow periods by removing a partial barrier.

Accomplishments

Metric Completed Originally
Proposed
Fish Passage
  Barriers Removed
  Miles Opened 1.50 1.50

Funding Details

SourceFunds
State$613,142
In-Kind Other$262,069
Report Total:$875,211


Project Map



Worksites

7211393    


  • Worksite Identifier: 7211393
  • Start Date:
  • End Date:
Area Description
Mill Creek Bridge

Location Information

  • Basin: Klamath (180102)
  • Subbasin: Scott (18010208)
  • Watershed: Indian Creek-Scott River (1801020805)
  • Subwatershed:
  • State: California
  • Recovery Domain: N CA - S Oregon
  • Latitude: 41.560777
  • Longitude: -122.9852

ESU

  • Southern Oregon/Northern California Coast Coho Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 875,211.00
    •      . . C.0.b Length of stream treated/protected .50
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      Scott River Watershed Council, 2005, Scott River Strategic Action Plan, SRWC, Etna, CA
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 875,211.00
      •      . . . . C.2.b.1 Length of stream made accessible 1.50
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.g.1 Bridge installed or improved at road stream crossingY (Y/N)
        •      . . . . . . C.2.g.2 Number of bridges installed or improved/upgraded 1
        •      . . . . . . C.2.g.3 Miles of stream made accessible by bridge installation or improvement/upgrade 1.50