East Branch Little North Fork LWD and Instream Barrier Modification

Salmonid Habitat Restoration and Acquisition

Fish Passage Improvement Instream Habitat
Project ID724684
Recovery DomainsN Central California Coast
Start Date06/01/2016
End Date03/05/2018
Year2015
StatusCompleted
Last Edited01/25/2024
 
1 - 1

Description    


Grantee added 46 wood structures over 0.27 miles by felling 60 streamside trees into the creek. The project also stabilized an 800 cubic yards of historic landslide debris that blocked the creek. The removal of the blockage increased salmoid access to 0.79 miles of instream habitat and prevented approximately 250 cubic yard of sediment from entering the channel.

Project Benefit    


Habitat complexity through installation of LWD structures and removal of a landslide barrier to fish migration.

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated .27 .27
Fish Passage
  Barriers Removed 1 1
  Miles Opened .79 .79

Funding Details

SourceFunds
State$55,883
Other$36,925
Report Total:$92,808


Project Map



Worksites

7211068    


  • Worksite Identifier: 7211068
  • Start Date:
  • End Date:
Area Description
EBLNF

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 39.3412
  • Longitude: -123.6608

ESU

  • Central California Coast Coho Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 204,723.00
    •      . . C.0.b Length of stream treated/protected .27
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      Downie, S., B. deWaard, E. Dudik, D. McGuire, and R. Rutland. 2006. Big River Basin Assessment Report. North Coast Watershed Assessment Program.
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 46,404.00
      •      . . . . C.2.b.1 Length of stream made accessible .79
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.c.1 Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
        •      . . . . . . C.2.c.2 Number of blockages/impediments/barriers removed/altered 1
      •      . . C.4 Instream Habitat ProjectY (Y/N)
        •      . . . . C.4.a Instream Habitat Funding 46,404.00
        •      . . . . C.4.b Total length of instream habitat treated .27
        •      . . . . C.4.d.1 Channel structure placementY (Y/N)
          •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
          •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .27
          •      . . . . . . C.4.d.5 Pools expected to be created through channel structure placement 0
          •      . . . . . . C.4.d.7 Number of structures placed in channel 46