Salmon and Steelhead Recovery

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project IDCCT15-1
Recovery DomainsUpper Columbia River
Start Date11/30/2015
End Date07/31/2017
Year2015
StatusCompleted
Last Edited01/25/2024
 
1 - 1

Description    


Provided tribal coordination with Upper Columbia River anadromous fish recovery processes, participated in watershed planning, and in other regional salmon and steelhead recovery forums utilizing FY15 funding. Provided senior level scientific support, development, guidance and implementation of key ESA recovery initiatives in the Okanogan subbasin utilizing FY15 funding. The actual end date was described to take into account the final invoicing and accounting that was necessary to close out the grant.

Project Benefit    


Contributed to an increase in tribal capacity to coordinate with regional salmon recovery efforts, and to develop and implement various watershed and subbasin plans utilizing FY15 funding. Key staff infrastructure ensured that core recovery projects were adequately funded, implemented, and monitored. Staff infrastructure identified cost-sharing opportunities that leveraged adequate funding. This project was necessary to implementing priority habitat actions for ESA-listed salmonids (Priority 1).

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$171,921
Report Total:$171,921


Project Map



Worksites

40247585    


  • Worksite Identifier: 40247585
  • Start Date: 11/02/2015
  • End Date: 07/01/2016
Area Description
Upper Columbia-Okanogan River

Location Information

  • Basin: Upper Columbia (170200)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Washington
  • Recovery Domain: Upper Columbia River
  • Latitude: 48.56410326039466
  • Longitude: -119.5193481445294

ESU

  • Upper Columbia River Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 171,921.00
    •      . . B.0.b.1 Area Encompassed 200.0
    •      . . B.0.b.2 Stream Miles Affected 60.00
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding 171,921.00
      •      . . . . B.1.b.2 Coordination on implementation of a Recovery PlanY (Y/N)
        •      . . . . . . B.1.b.2.a
          Name of the Recovery Plan Implemented
          Upper Columbia Salmon Recovery Board (UCSRB). 2007. Upper Columbia Spring Chinook Salmon and Steelhead Recovery Plan. National Oceanic and Atmospheric Administration, West Coast Region. Available at: http://www.ucsrb.org/library/plans/
        •      . . . . . . B.1.b.2.b
          Description and scope of the Recovery Plan implemented
          The UCSR plan identifies all-H measures that assist in the recovery of listed species in the UC ESU. Four major watersheds are targeted for recovery efforts including: 1) Wenatchee; 2) Entiat; 3) Methow; and 4) Okanogan.