Upper Columbia Basin Salmon Recovery Planning, Implementation and Coordination
Salmonid Restoration Planning and Assessments
|
CCT13-1 | Upper Columbia River | 09/30/2013 | 07/31/2015 | 2013 | Completed | 01/14/2025 | |
| |
Description
Provided tribal coordination with Upper Columbia River anadromous fish recovery processes, participated in watershed planning, and in other regional salmon and steelhead recovery forums utilizing FY13 funding. Provided senior level scientific support, development, guidance and implementation of key ESA recovery initiatives in the Okanogan subbasin utilizing FY13 funding.
Project Benefit
Contributed to an increase in tribal capacity to coordinate with regional salmon recovery efforts, and to develop and implement various watershed and subbasin plans utilizing FY13 funding. Key staff infrastructure ensured that core recovery projects were adequately funded, implemented, and monitored. Staff infrastructure identified cost-sharing opportunities that leveraged adequate funding. This project was necessary to implementing priority habitat actions for ESA-listed salmonids (Priority 1).
Funding Details |
PCSRF | $200,000 |
Report Total: | $200,000 |
|
| |
Worksites
37255679
- Worksite Identifier: 37255679
- Start Date:
- End Date:
Area Description
Upper Columbia
Location Information
- Basin: Upper Columbia (170200)
- Subbasin: 17020006
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain: Upper Columbia River
- Latitude: 48.56410326
- Longitude: -119.496002197
ESU
- Upper Columbia River Steelhead DPS
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 200,000.00
- . . B.0.b.1
Area Encompassed 200.0
- . . B.0.b.2
Stream Miles Affected 52.00
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 200,000.00
- . . . . B.1.b.2
Coordination on implementation of a Recovery PlanY (Y/N)
- . . . . . . B.1.b.2.a
Name of the Recovery Plan Implemented | |
Upper Columbia Salmon Recovery Board (UCSRB). 2007. Upper Columbia Spring Chinook Salmon and Steelhead Recovery Plan. National Oceanic and Atmospheric Administration, West Coast Region. Available at: http://www.ucsrb.org/library/plans/ |
- . . . . . . B.1.b.2.b
Description and scope of the Recovery Plan implemented | |
Implemented measures outlined in the referenced Upper Columbia Salmon Recovery Plan. Developed the "Habitat Report Card" for listed UC Steelhead (as outlined for abundance, productivity and spatial structure and diversity pg. 33 of UCSR Plan). |
|
|