Description    


Four culverts on the Kenai Peninsula Borough roads were replaced and one flow control structure within a Kenai Peninsula Borough right-of-way was repaired as follows:

Kenai River tributary, Soldotna: A culvert on a tributary of the Kenai River, formerly a fish passage barrier, was replaced with a stream simulation culvert.
Moose River-Moose River Drive: A culvert on a tributary of the Moose River, formerly a fish passage barrier, was replaced with a stream simulation culvert.
Bishop Creek-Paradise Lane: A culvert on Bishop Creek where is passes under Paradise Land, formerly a fish passage barrier, was replaced with a stream simulation culvert. This crossing is at the mouth of a lake, so although fish passage was repaired, reporting stream miles made accessible is not appropriate; rather, the square mileage of the lake is included in the metrics.
Bishop Creek-Vandemere Road: A culvert on Bishop Creek where is passes under Vandemere Road, formerly a fish passage barrier, was replaced with a stream simulation culvert.
Stickleback Road: An existing concrete flow control structure (partially collapsed) was replaced with a new concrete hydraulic step and retaining wall, repairing fish passage and preventing future blockage due to a full collapse.

In addition, materials were purchased for the replacement of a culvert on a tributary of the Kenai River with a bridge; construction was undertaken with other funds.

Replacing the existing culverts/structure with stream simulation structures restored unimpeded passage of juvenile and adult salmonids to 1.8 kilometers and 49 hectares of documented rearing habitat.

Project Benefit    


This project will enhance salmonid habitat in the KPB by restoring free and clear movement of juvenile salmonids at five road crossings. Restoring unimpeded fish passage will increase the availability of productive upstream habitats (including wetlands) to rearing juveniles. In addition, sizing the culverts to pass debris and sediment as well as water during a 100 year flood event will greatly reduce the likelihood of catastrophic road failures introducing large volumes of sediment into streams.

Accomplishments

Metric Completed Originally
Proposed
Fish Passage
  Barriers Removed 1 1
  Miles Opened 1.12 .82

Funding Details

SourceFunds
PCSRF$302,344
Other$99,774
Report Total:$402,118


Project Map



Worksites

Bishop Creek Paradise    


  • Worksite Identifier: Bishop Creek Paradise
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Kenai Peninsula (190203)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Alaska
  • Recovery Domain:
  • Latitude: 60.692
  • Longitude: -151.261

ESU

  • Un-Named ESU Sockeye
  • Un-Named ESU Coho

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 73,734.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      None
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 73,734.00
      •      . . . . C.2.b.1 Length of stream made accessible .00
      •      . . . . C.2.b.2 Square miles of streambed made accessible.2 (Square miles)
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.f.1 Culvert installed or improved at road stream crossingY (Y/N)
        •      . . . . . . C.2.f.2 Number of culverts installed or improved 1
        •      . . . . . . C.2.f.3 Miles of stream made accessible by culvert installation/upgrade .00

Kenai River    


  • Worksite Identifier: Kenai River
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Kenai Peninsula (190203)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Alaska
  • Recovery Domain:
  • Latitude: 60.5277
  • Longitude: -150.984

ESU

  • Un-Named ESU Coho

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 128,400.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      none
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.12 Pre-Restoration Acquisitions And Nursery OperationsY (Y/N)
      •      . . . . C.12.a Pre-restoration funding 128,400.00
      •      . . . . C.12.b.1 Restoration materialsY (Y/N)
        •      . . . . . . C.12.b.2
          Describe what was purchased
          A culvert was purchased to replace a fish passage barrier on a tributary of the Kenai River; the restoration took place using other funds, opening up 1.2 miles of habitat.

Stickle Back Road    


  • Worksite Identifier: Stickle Back Road
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Kenai Peninsula (190203)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Alaska
  • Recovery Domain:
  • Latitude: 60.729
  • Longitude: -151.168

ESU

  • Un-Named ESU Sockeye
  • Un-Named ESU Coho

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 3,890.00
    •      . . C.0.b Length of stream treated/protected 1.12
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      none
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 3,890.00
      •      . . . . C.2.b.1 Length of stream made accessible .10
      •      . . . . C.2.b.2 Square miles of streambed made accessible.1 (Square miles)
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.c.1 Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
        •      . . . . . . C.2.c.2 Number of blockages/impediments/barriers removed/altered 1

Moose River    


  • Worksite Identifier: Moose River
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Kenai Peninsula (190203)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Alaska
  • Recovery Domain:
  • Latitude: 60.538
  • Longitude: -150.756

ESU

  • Un-Named ESU Chinook
  • Un-Named ESU Coho

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 53,727.00
    •      . . C.0.b Length of stream treated/protected 1.12
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      none
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 53,727.00
      •      . . . . C.2.b.1 Length of stream made accessible .30
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.f.1 Culvert installed or improved at road stream crossingY (Y/N)
        •      . . . . . . C.2.f.2 Number of culverts installed or improved 1
        •      . . . . . . C.2.f.3 Miles of stream made accessible by culvert installation/upgrade .30

Bishop Creek Vandevere    


  • Worksite Identifier: Bishop Creek Vandevere
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Kenai Peninsula (190203)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Alaska
  • Recovery Domain:
  • Latitude: 60.692
  • Longitude: -151.255

ESU

  • Un-Named ESU Sockeye
  • Un-Named ESU Coho

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 73,734.00
    •      . . C.0.b Length of stream treated/protected .42
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      None
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 73,734.00
      •      . . . . C.2.b.1 Length of stream made accessible .42
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.f.1 Culvert installed or improved at road stream crossingY (Y/N)
        •      . . . . . . C.2.f.2 Number of culverts installed or improved 1
        •      . . . . . . C.2.f.3 Miles of stream made accessible by culvert installation/upgrade .42

Soldotna Cr    


  • Worksite Identifier: Soldotna Cr
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Kenai Peninsula (190203)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Alaska
  • Recovery Domain:
  • Latitude: 60.528
  • Longitude: -150.984

ESU

  • Un-Named ESU Coho

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 68,633.00
    •      . . C.0.b Length of stream treated/protected 1.12
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      none
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 68,633.00
      •      . . . . C.2.b.1 Length of stream made accessible .30
      •      . . . . C.2.b.2 Square miles of streambed made accessible0 (Square miles)
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.f.1 Culvert installed or improved at road stream crossingY (Y/N)
        •      . . . . . . C.2.f.2 Number of culverts installed or improved 1
        •      . . . . . . C.2.f.3 Miles of stream made accessible by culvert installation/upgrade .30