Bummer Spurs Watershed Rehabilitation Project
Salmonid Habitat Restoration and Acquisition
|
720220 | N CA - S Oregon | 06/01/2005 | 03/31/2008 | 2003 | Completed | 01/26/2024 | |
| |
Description
In 2005, 3.9 miles of road with 16 crossings was decommissioned. No work in 2006.
In 2007 grantee decommissioned 3.0 miles of road and 26 stream crossings
Project Benefit
Project will improve spawning and rearing habitat for coho and Chinook salmon and steelhead and cutthroat trout in sections of Bummer Lake Creek and East Fork Mill Creek. It will improve water quality and riparian corridors at excavated stream crossings.
Funding Details |
PCSRF | $742,785 |
Report Total: | $742,785 |
|
| |
Worksites
7208847
- Worksite Identifier: 7208847
- Start Date:
- End Date:
Area Description
Mill Creek Watershed, E. Fk. - Mud Spur Rd (decommission road)
Location Information
- Basin: Northern California Coastal (180101)
- Subbasin: Smith River
- Watershed: Smith River-Frontal Pacific Ocean
- Subwatershed:
- State: California
- Recovery Domain: N CA - S Oregon
- Latitude: 41.739899
- Longitude: -124.051774
ESU
- Southern Oregon/Northern California Coast Coho Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 148,557.00
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Mill Creek Interim Management Recommendations (Clearwater Biologists) |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 148,557.00
- . . . . C.6.b.1
Acres of upland habitat area treated .0
- . . . . C.6.b.2
Miles of road treated in upland area 1.88
- . . . . C.6.d.1
Road closure / abandonmentY (Y/N)
- . . . . . . C.6.d.2
Miles of road closed / abandoned 1.88
7204154
- Worksite Identifier: 7204154
- Start Date:
- End Date:
Area Description
Mill Creek Watershed, E. Fk. - B and B Spur (decommission road)
Location Information
- Basin: Northern California Coastal (180101)
- Subbasin: Smith River
- Watershed: Smith River-Frontal Pacific Ocean
- Subwatershed:
- State: California
- Recovery Domain: N CA - S Oregon
- Latitude: 41.730123
- Longitude: -124.042884
ESU
- Southern Oregon/Northern California Coast Coho Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 148,557.00
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Mill Creek Interim Management Recommendations (Clearwater Biologists) |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 148,557.00
- . . . . C.6.b.1
Acres of upland habitat area treated .0
- . . . . C.6.b.2
Miles of road treated in upland area 2.88
- . . . . C.6.d.1
Road closure / abandonmentY (Y/N)
- . . . . . . C.6.d.2
Miles of road closed / abandoned 2.88
7204155
- Worksite Identifier: 7204155
- Start Date:
- End Date:
Area Description
Mill Creek Watershed, E. Fk. - Lower Spur Rd (decommission road)
Location Information
- Basin: Northern California Coastal (180101)
- Subbasin: Smith River
- Watershed: Smith River-Frontal Pacific Ocean
- Subwatershed:
- State: California
- Recovery Domain: N CA - S Oregon
- Latitude: 41.719641
- Longitude: -124.058095
ESU
- Southern Oregon/Northern California Coast Coho Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 148,557.00
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Mill Creek Interim Management Recommendations (Clearwater Biologists) |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 148,557.00
- . . . . C.6.b.1
Acres of upland habitat area treated .0
- . . . . C.6.b.2
Miles of road treated in upland area 2.03
- . . . . C.6.d.1
Road closure / abandonmentY (Y/N)
- . . . . . . C.6.d.2
Miles of road closed / abandoned 2.03
7204157
- Worksite Identifier: 7204157
- Start Date:
- End Date:
Area Description
Mill Creek Watershed, E. Fk. - Childs Hill Road (decommission road)
Location Information
- Basin: Northern California Coastal (180101)
- Subbasin: Smith River
- Watershed: Smith River-Frontal Pacific Ocean
- Subwatershed:
- State: California
- Recovery Domain: N CA - S Oregon
- Latitude: 41.723649
- Longitude: -124.051536
ESU
- Southern Oregon/Northern California Coast Coho Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 148,557.00
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Mill Creek Interim Management Recommendations (Clearwater Biologists) |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 148,557.00
- . . . . C.6.b.1
Acres of upland habitat area treated .0
- . . . . C.6.b.2
Miles of road treated in upland area .44
- . . . . C.6.d.1
Road closure / abandonmentY (Y/N)
- . . . . . . C.6.d.2
Miles of road closed / abandoned .44
7204149
- Worksite Identifier: 7204149
- Start Date:
- End Date:
Area Description
Mill Creek Watershed, E. Fk. - Ramp Spur Rd (decommission road)
Location Information
- Basin: Northern California Coastal (180101)
- Subbasin: Smith River
- Watershed: Smith River-Frontal Pacific Ocean
- Subwatershed:
- State: California
- Recovery Domain: N CA - S Oregon
- Latitude: 41.727912
- Longitude: -124.062295
ESU
- Southern Oregon/Northern California Coast Coho Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 148,557.00
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Mill Creek Interim Management Recommendations (Clearwater Biologists) |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 148,557.00
- . . . . C.6.b.1
Acres of upland habitat area treated .0
- . . . . C.6.b.2
Miles of road treated in upland area .97
- . . . . C.6.d.1
Road closure / abandonmentY (Y/N)
- . . . . . . C.6.d.2
Miles of road closed / abandoned .97
|
|