Mill Creek Watershed Restoration Project

Salmonid Habitat Restoration and Acquisition

Instream Habitat Upland Habitat And Sediment
Project ID704252
Recovery DomainsN Central California Coast
Start Date06/01/2001
End Date10/25/2002
Year2001
StatusCompleted
Last Edited01/27/2024
 
1 - 1

Description    


Provided cost-effective treatment for sediment yield at identified sites in the Mill Creek Watershed and along Matthews Ranch Rd. Conducted sediment yield mitigation through road upgrades, crossing removals, and streambank armoring in the riparian zone.

Project Benefit    


Improve: Excessive sediment

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated .01 .01

Funding Details

SourceFunds
State$27,803
Report Total:$27,803


Project Map



Worksites

7004050    


  • Worksite Identifier: 7004050
  • Start Date:
  • End Date:
Area Description
Mill Creek - Site 22 (bank stabilization/LWD modification)

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed: Mattole River
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 40.29177
  • Longitude: -124.296431

ESU

  • California Coastal Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 6,178.00
    •      . . C.0.b Length of stream treated/protected .01
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      N/A
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 3,089.21
      •      . . . . C.4.b Total length of instream habitat treated .01
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .01
        •      . . . . . . C.4.d.5 Pools expected to be created through channel structure placement 0
        •      . . . . . . C.4.d.7 Number of structures placed in channel 1
      •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
        •      . . . . C.6.a Upland Habitat / Sediment Funding 3,089.21
        •      . . . . C.6.b.1 Acres of upland habitat area treated .0
        •      . . . . C.6.b.2 Miles of road treated in upland area .21
        •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
          •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .21

7004051    


  • Worksite Identifier: 7004051
  • Start Date:
  • End Date:
Area Description
Mill Creek - Site 23 (remove flow impediment)

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed: Mattole River
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 40.296291
  • Longitude: -124.306586

ESU

  • California Coastal Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 6,178.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      N/A
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 3,089.21
      •      . . . . C.4.b Total length of instream habitat treated .00
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .00
        •      . . . . . . C.4.d.5 Pools expected to be created through channel structure placement 0
        •      . . . . . . C.4.d.7 Number of structures placed in channel 1
      •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
        •      . . . . C.6.a Upland Habitat / Sediment Funding 3,089.21
        •      . . . . C.6.b.1 Acres of upland habitat area treated .0
        •      . . . . C.6.b.2 Miles of road treated in upland area .21
        •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
          •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .21

7004052    


  • Worksite Identifier: 7004052
  • Start Date:
  • End Date:
Area Description
Mill Creek Watershed - Site 17 (decommission crossing)

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed: Mattole River
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 40.292403
  • Longitude: -124.29654

ESU

  • California Coastal Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 3,089.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      N/A
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
      •      . . . . C.6.a Upland Habitat / Sediment Funding 3,089.21
      •      . . . . C.6.b.1 Acres of upland habitat area treated .0
      •      . . . . C.6.b.2 Miles of road treated in upland area .21
      •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
        •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .21

7207676    


  • Worksite Identifier: 7207676
  • Start Date:
  • End Date:
Area Description
Mill Creek Watershed - Sites 1-7 (road upgrades)

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed: Mattole River
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 40.29572
  • Longitude: -124.31618

ESU

  • California Coastal Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 3,089.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      N/A
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
      •      . . . . C.6.a Upland Habitat / Sediment Funding 3,089.21
      •      . . . . C.6.b.1 Acres of upland habitat area treated .0
      •      . . . . C.6.b.2 Miles of road treated in upland area .21
      •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
        •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .21

7207677    


  • Worksite Identifier: 7207677
  • Start Date:
  • End Date:
Area Description
Mill Creek Watershed - Sites 8-10 (road upgrades and decommissioning)

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed: Mattole River
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 40.281183
  • Longitude: -124.29986

ESU

  • California Coastal Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 3,089.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      N/A
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
      •      . . . . C.6.a Upland Habitat / Sediment Funding 3,089.21
      •      . . . . C.6.b.1 Acres of upland habitat area treated .0
      •      . . . . C.6.b.2 Miles of road treated in upland area .21
      •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
        •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .21

7207678    


  • Worksite Identifier: 7207678
  • Start Date:
  • End Date:
Area Description
Mill Creek Watershed - Sites 11-15 (road upgrades)

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed: Mattole River
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 40.279186
  • Longitude: -124.297396

ESU

  • California Coastal Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 3,089.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      N/A
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
      •      . . . . C.6.a Upland Habitat / Sediment Funding 3,089.21
      •      . . . . C.6.b.1 Acres of upland habitat area treated .0
      •      . . . . C.6.b.2 Miles of road treated in upland area .21
      •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
        •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .21

7207679    


  • Worksite Identifier: 7207679
  • Start Date:
  • End Date:
Area Description
Mill Creek Watershed - Sites 16-21 (road decommissioning)

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed: Mattole River
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 40.283898
  • Longitude: -124.298452

ESU

  • California Coastal Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 3,089.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      N/A
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
      •      . . . . C.6.a Upland Habitat / Sediment Funding 3,089.21
      •      . . . . C.6.b.1 Acres of upland habitat area treated .0
      •      . . . . C.6.b.2 Miles of road treated in upland area .21
      •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
        •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .21