King Solomon Mine Tailings Dams Reclamation Project

Salmonid Habitat Restoration and Acquisition

Instream Habitat
Project ID703754
Recovery DomainsN CA - S Oregon
Start Date06/01/2002
End Date03/02/2004
Year2001
StatusCompleted
Last Edited01/26/2024
 
1 - 1

Description    


Excavated and removed unstable portions of 2 remnant tailings dams and stabilized several segments of stream channel to eliminate the threat of a large volume sediment release into Matthews Creek.

Project Benefit    


The project’s overall goal was restoration and protecting of Late Successional Reserve and summer and winter run steelhead trout and Chinook and coho salmon habitat by reducing sediment input to Matthews Creek from unstable tailings dams and eroding streambanks within the project area.

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated .19 .19

Funding Details

SourceFunds
PCSRF$101,072
Report Total:$101,072


Project Map



Worksites

7003053    


  • Worksite Identifier: 7003053
  • Start Date:
  • End Date:
Area Description
Matthews Creek - Sites 1-4 (dam modification and bank stabilization)

Location Information

  • Basin: Klamath (180102)
  • Subbasin:
  • Watershed: South Fork Salmon River
  • Subwatershed:
  • State: California
  • Recovery Domain: N CA - S Oregon
  • Latitude: 41.181582
  • Longitude: -123.172671

ESU

  • Southern Oregon/Northern California Coast Coho Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 101,072.00
    •      . . C.0.b Length of stream treated/protected .19
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      N/A
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 101,072.00
      •      . . . . C.4.b Total length of instream habitat treated .19
      •      . . . . C.4.e.1 Streambank stabilization Y (Y/N)
        •      . . . . . . C.4.e.2 Material Used For Streambank Stabilization (LOV)
        •      . . . . . . C.4.e.3 Miles of streambank stabilized .19