Develop Local Okanogan River Basin Steelhead Broodstock - Phase I

Salmonid Hatcheries and Harvest Management

Hatchery Production
Project IDCCT01-5
Recovery DomainsUpper Columbia River
Start Date06/15/2002
End Date08/31/2004
Year2001
StatusCompleted
Last Edited01/27/2024
 
1 - 1

Description    


Funding for this project became available in June of 2002. An initial draft Okanogan River steelhead HGMP was completed late 2002. Between 2002 and late 2003, that HGMP underwent multiple reviews and revisions. A final HGMP is expected to be completed in late 2003. Planning associated with development of broodstock collection facilities in Omak Creek was completed in 2003. Delays in initial funding, delays in development of the HGMP, and ultimately the reprioritization of the Cassimer facilities to raise additional sockeye smolt - caused the Colville Tribes to change the proposed location of raceways for the steelhead broodstock program. After reviewing options and cost considerations, the Colville Tribes elected to construct the necessary raceways at Colville Tribes Bridgeport Hatchery. The Bridgeport raceway construction was completed in 2003. No fish were collected in the first Phase of the project because final permits were not in place. The second phase of the project was funded with PCSRF FY03 funds (project identification number CCT03-2).

Project Benefit    


Increase genetic and life-history diversity, and improve survival, of naturally produced Upper Columbia ESU summer steelhead.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$170,225
Report Total:$170,225


Project Map



Worksites

1240    


  • Worksite Identifier: 1240
  • Start Date: 06/15/2002
  • End Date: 08/31/2003
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Upper Columbia (170200)
  • Subbasin: Chief Joseph
  • Watershed:
  • Subwatershed:
  • State: Washington
  • Recovery Domain: Upper Columbia River
  • Latitude: 47.9894356308357
  • Longitude: -119.645237763848

ESU

  • Upper Columbia River Steelhead DPS
  • Upper Columbia River Spring-run Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • D.0 Salmonid Hatcheries and Harvest ManagementY (Y/N)
    •      . . D.0.a Hatchery and harvest mgmt. funding 170,225.00
    •      . . D.1 Hatchery Production ProjectY (Y/N)
      •      . . . . D.1.a Hatchery Production Funding 170,225.00
      •      . . . . D.1.c.1 Hatchery operations - facility or equipmentY (Y/N)